To change the order in which fields are listed in the schedule, use the up/down arrows at the left edge of each row to move the field up or down.
See also Schemes Fields Panel.
Sort By Value (Ascending/Descending)
For any field in Scheme Settings: Activate the up/down arrow to sort the items of this field in ascending/descending order; or leave this field blank, for “None”. “None” means that this field will not be taken into consideration when sorting.
Note: If “Show Headline” is checked, and the first field’s sorting arrow is blank (“None”), then the sorting is automatically set to a descending order based on the first field (the source of the Headline)
In this example: the Volume field has activated the up arrow. The listed walls that are of the same structure type will be listed in order of their volume (top value the highest).