The Surface Schedule is the third type of interactive schedule, alongside Element Lists and Component Lists.
Note: Before using the Surface Schedule feature, make sure you are not working in “legacy” intersection mode. (Uncheck the “Use legacy intersection” box at Options > Project Preferences > Legacy.)
Surface Schedule Fields
In Scheme Settings, use the available fields as needed to adjust the content of your Surface lists.
For details on setting up a scheme, see Scheme Settings Dialog Box (Interactive Schedule).
Surface Differs from Building Materials
This field is displayed in the schedule as a checkbox (e.g. entitled “Painted”) to indicate it has been “painted over” with an override.
Note: This field is not evaluated for Openings, which do not have Building Materials.
Surface Schedule: Predefined schemes